En todo contrato de exploración y explotación de petróleo de propiedad nacional se estipulará que seis (6) meses antes, por lo menos, de vencerse el período inicial de exploración, el contratista deberá instalar dentro de la concesión por lo menos un equipo completo de perforación, que mantendrá trabajando con la debida asiduidad.
Decreto 1056 de 1953 →In force
Article 145
Decreto 1056 de 1953 · Por el cual se expide el Código de Petróleos
The official text of this article is in Spanish and is shown as published by the Colombian authorities.
01
Text of the article
✓Verbatim text as it appears in the provision. Hard data, citable.
02
Constitutional history
Every Constitutional Court ruling that has reviewed this article, in chronological order. Follow how the doctrine evolved: each ruling links to its record.
This article has no constitutional review recorded in the Court’s graph. It may not have been challenged yet, or the challenge may not have reached a decision on the merits.